The project was the fitout of the new Manufacture Plant at Sari Village - Moraiya of around 65,000 sq.ft .The building consists of Open Plant area for manufacture Thickners and Export Across the world and Admin building . .
Electrical scope of works comprised installation of PCC panel with Bu Coupler , switchgear, Plant & Office lighting & emergency lighting, installation. The installation was just started on August 2016 .