The project was the fitout of the new |Staff Canteen area At Sanand of around 8,000 sq.ft .The building consists of around seating arrangement of 250 person , Kitchen area and toilets.
Electrical scope of works comprised installation of lighting & emergency lighting, installation. The installation was completed between March – 2013 to May – 2013
Plumbing Scope of works comprised installation of Internal PVC Plumbing Work of Plant .The installation was completed between March – 2013 to May - 2013