Triveni Polymer ( Gerresheimer)
The project was the fit-out of the New Manufacturing Facility at Kausamba - Surat Gujarat of 65,000 sq ft of constructed area.The building consists Ground + 2 Floor Open Area for Machinery , Storage area and Utility Area and Utility Building .
The electrical scope of works comprised Electrical Load Liaison, SITC Of New 1 now of 1500 Kva Tx , HT Rmu & VCB Panel , SITC of PCC panel, APFC Panel ,PDB Panel, LT Cabling, PDB Cabling , Power Socket work , Cable Tray and Its fabrication job & Plant lighting.
The installation was started in December 2021 & completed in April 2022.
Client : – Triveni Polymer Pvt Ltd
Consultant - S3M Consultant
Project : – Contract
Project engineer:- Rakesh Prajapati/Darshan nakum