Aatmarnirbhar Solar Pvt Ltd

AatmarNibhar Solar Company are New In Manufacturing process of High Output Solor Panel with state of the art Facility and New Technology Machinery .

The project was the fit-out of the New Manufacturing Facility at Kapadvanj Gujarat of 65,000 sq ft of constructed area.The building consists Open Area for Machinery , Storage area and Admin Area and Building .

The electrical scope of works comprised Electrical Load Liaison, SITC Of New 1 now of 750 Kva Tx , HT Rmu & VCB Panel , ITC of new PCC panel, APFC Panel , LT Cabling, PDB Cabling , Power Socket work , Cable Tray and Its fabrication job & Plant lighting.

The installation was started in January 2022 & completed in April 2022.

Client : – Aatmarnirbhar Solar Pvt Ltd
Consultant – Prachtovoll Enginers
Project : – Contract
Project engineer:- Girish Prajapati

Pilate Studio

The project was the fitout of the new Showroom of around 1,500 sq.ft .The showroom consists of Different Display area in Ahmedabad . Electrical scope of works comprised installation of lighting & emergency lighting, installation, Communication system installation , CCTV & PA Work. The installation was completed in June 2024.

The project was the fitout of the new Showroom of around 1,500 sq.ft .The showroom consists of Different Display area in Ahmedabad . Electrical scope of works comprised installation of lighting & emergency lighting, installation, Communication system installation , CCTV & PA Work. The installation was completed in June 2024.