This project involved the fit-out of a state-of-the-art manufacturing plant located at the Bavla-Rajkot Highway, covering a vast area of 7,00,000 sq.ft. The facility includes:
– An Open Plant Area for machinery assembly
– A TCC Machinery building with Admin & Lab Areas
– A separate Utility building
Our scope of work included the supply and installation of TX, DG, HT & LT Panels, plant lighting, machine cabling, cable tray fabrication, earthing, lightning arrestors, and internal electrical installations across the plant.
The installation was carried out from December 2023 to January  2025, delivering a fully operational plant ready for the next phase of production.

Project Type:

Contract

Consultant:

VMS Consultant

Client:

Trutzler India Pvt Ltd

Project Completed:

January 2025

Pilate Studio

The project was the fitout of the new Showroom of around 1,500 sq.ft .The showroom consists of Different Display area in Ahmedabad . Electrical scope of works comprised installation of lighting & emergency lighting, installation, Communication system installation , CCTV & PA Work. The installation was completed in June 2024.

The project was the fitout of the new Showroom of around 1,500 sq.ft .The showroom consists of Different Display area in Ahmedabad . Electrical scope of works comprised installation of lighting & emergency lighting, installation, Communication system installation , CCTV & PA Work. The installation was completed in June 2024.