Tata autocomp Systems ltd(TACO)

Industrial Project: – Crystal India Logistic – Project TACO (Tata autocomp Systems ltd)

The project was the fit out of the new Manufacture & Storage Plant at Sanand industrial area, Ahmedabad of around 410000 sq.ft .The building consists of Open Plant area for Storage and some area for manufacturing.

Electrical scope of works comprised installation of LT Panel , Plant Lighting work, Cabel tray work , Street Lighting work and internal electrical work for areas. Lighting Arrestor Work for the Same .
The installation was started on September 2022 and completed on December 2022.

Detail Of Distribution board with Cable tray Dressing and execution work is point to look .

Project :- Contract
Consultant : -VMS Consultant
Client :- Crystal Group
Project Engineer: – Pragnesh Suthar

Project Partner: –

Lighting -Bajaj
Cable – Avocab
Cable tray – Ramdev –
Switchgear & Push Button – L&T
Power Socket – Schneider

Pilate Studio

The project was the fitout of the new Showroom of around 1,500 sq.ft .The showroom consists of Different Display area in Ahmedabad . Electrical scope of works comprised installation of lighting & emergency lighting, installation, Communication system installation , CCTV & PA Work. The installation was completed in June 2024.

The project was the fitout of the new Showroom of around 1,500 sq.ft .The showroom consists of Different Display area in Ahmedabad . Electrical scope of works comprised installation of lighting & emergency lighting, installation, Communication system installation , CCTV & PA Work. The installation was completed in June 2024.